Traffic Impacts

This page will be updated weekly to communicate anticipated traffic impacts during construction.

Week of 21-07-31 to 21-08-06

Travel Delay (Minutes):

Eastbound: 5 Westbound: 5

Anticipated Traffic Impacts:

  • Nightly Hwy 401 eastbound and westbound lane reductions for median work at the Hespeler Road interchange, paving operations and traffic realignment.
  • Nightly intermittent ramp closures.
  • Franklin Blvd Interchange on and off ramps closed until August 2021.
  • Two day closure of the Hespeler Road interchange westbound on ramp (south to west ramp) from August 6- August 8, 2021 (Weather dependent).

View Archive of Traffic Impacts

.