Construction Activities

Information about upcoming and previous construction activities can be found on this page.

Construction Progress for Past Month

November 2021

  • Installation of electrical ducts and manholes for luminaires and high mast poles throughout the contract.
  • Hespeler Rd North structure continues
  • High mast pole caps and footings in Stage 2G are complete
  • Median sewers are complete in stage 2G
  • Earth excavation and granulars for stage 2G.
  • Median tall wall is complete for stage 2G.
  • Median paving for stage 2G and Hespeler Rd continues.

Construction Work Scheduled for Next Month

December 2021

  • Installation of electrical ducts and manholes for luminaires and high mast poles throughout the contract.
  • Complete the Hespeler Rd North structure Paving and expansion joint works and opening structure to traffic
  • Complete the Granulars and SP 19 shoulders for stage 2G.
  • Complete the Median paving for stage 2G and Hespeler Rd
  • Stage traffic into winter configuration on Hespeler Road and Hwy 401
  • 36 hour closure of the Hespeler SW ramp to tie in new ramp and to complete some preparation work for Hespeler Road staging in the spring.

.