Construction Activities

Information about upcoming and previous construction activities can be found on this page.

Construction Progress for Past Month

August 2021

  • Installation of electrical ducts and manholes for luminaires and high mast poles throughout the contract.
  • Pond excavations
  • WBL - Stage 2C work in and flipped traffic into stage 2D and then into stage 2E.
  • EBL - Contractor is in stage 2G at west end and stage 2E at east end.
  • 36 hour closure to tie in the Hespeler E-NS ramp to the new alignment.
  • Hespeler Rd North structure – abutments and median pier work continue with girder erection and deck construction.
  • Complete work at carpool lot

Construction Work Scheduled for Next Month

September 2021

  • Installation of electrical ducts and manholes for luminaires and high mast poles throughout the contract.
  • Pond excavations
  • Stage traffic into stage 2e and stage 2g on highway 401
  • Hespeler Rd North structure –Deck construction.
  • High mast poles and footings
  • Median sewers

.